Free download
Custom Home Construction Schedule Template
A realistic residential phase schedule covering all 11 construction phases, from preconstruction through certificate of occupancy. 41 tasks, 9 columns, and honest notes about what varies by jurisdiction, weather, and scope.
Schedules vary by jurisdiction, weather, project scope, inspection requirements, trade availability, and owner selections. Use this as a starting point and adjust durations and phases to match your project.
Phase overview
What the schedule covers, phase by phase.
The template follows the standard sequence of a residential custom home build. Each phase is listed with its task count and a note on what typically affects timing for that phase.
Preconstruction
3 tasks
Design, engineering, survey. Typically 30–90 days.
Permitting
2 tasks
Submittal and approval. Varies significantly by jurisdiction.
Sitework
2 tasks
Clearing, grading, underground utilities.
Foundation
3 tasks
Footings, walls, slab. Allow cure time before framing.
Framing
4 tasks
Structure, roof, windows, doors, and framing inspection.
Dry-in
2 tasks
Housewrap and roofing. Protects the structure for rough-ins.
Rough-ins
4 tasks
Electrical, plumbing, HVAC, and rough-in inspections.
Insulation & Drywall
3 tasks
Insulation approval before drywall hang and finish.
Interior Finishes
7 tasks
Painting, cabinets, trim, flooring, finish trades.
Exterior Finishes
4 tasks
Siding, garage doors, driveway, and landscaping.
Inspections & Closeout
7 tasks
Final inspections, punch list, CO, lien waivers, owner handoff.
Column guide
What each column tracks and how to use it.
Phase
The construction phase this task belongs to. Used for grouping and filtering by milestone.
Task
The specific work item within the phase. Be as specific as your sub agreements and inspection requirements demand.
Predecessor
What task must be complete before this one can start. Leave blank for tasks with no dependency.
Planned Start
Target start date in YYYY-MM-DD format. Adjust as the project progresses.
Planned Finish
Target completion date. Update when actual completion differs from plan.
Duration (days)
The number of calendar days planned for this task. Note that this is a planning estimate, not a guarantee.
Responsible Party
The contractor, sub, or owner responsible for completing this task.
Status
Not Started | In Progress | Complete | Delayed | On Hold. Update as the project moves.
Notes
Any context that doesn't fit the other columns: inspection requirements, lead times, material orders, weather holds.
How to use this template
Getting the most out of a construction schedule.
Delete the instruction rows first
The template includes two instruction rows at the top. Delete those before adding your project's actual dates. Keep the column headers in row 1.
Replace YYYY-MM-DD placeholders with real dates
Start with your planned groundbreak date and work forward through the phases. Update Planned Start and Planned Finish as you learn more. Your permit approval timeline is usually the first thing that changes.
Align phase names with your lender's draw schedule
If your project uses a construction loan, confirm that your phase names match the milestone language your lender and inspector will use. "Foundation complete" means different things to different lenders. Align on specific definitions before the loan closes.
Adjust durations for your market and scope
The template uses typical residential durations. Your framing sub might be faster or slower. Your permit review might take 4 weeks or 10 weeks. Adjust every duration based on your actual subcontractor commitments and local conditions.
Update status as you go
A schedule that isn't updated is just a plan. Update the Status column weekly, or whenever a task completes, so you can see what's on track, what's delayed, and what's coming up next.
Use it to prep for draw submissions
Before submitting a draw, review the schedule to confirm the phase milestone is actually complete. The schedule is a useful cross-reference against your draw checklist and photo documentation.
Download
Get the template. No sign-up required.
Download the CSV and open it in Microsoft Excel, Google Sheets, Numbers, or any spreadsheet app. Delete the instruction rows, replace the placeholder dates with your project's actual timeline, and adjust durations to match your market and scope.
Schedules vary by jurisdiction, weather, project scope, trade availability, and owner selections. This template is a starting point, not a guarantee of actual timelines.
Connect your schedule to your draws
Builtly tracks phase completion and ties it directly to your draw packages.
Phase milestones in Builtly drive your draw schedule. When a phase is marked complete, the draw checklist populates: photos, lien waivers, budget figures. Submit a clean package without hunting for documentation.
See draw management